Filing Your Construction Lien on Time

2019-08-19T14:46:36-05:00August 22nd, 2019|Construction Contractor Advisor, Construction Lien, Nebraska Construction Law|

As we have discussed in other blog posts, filing a construction lien on time is critical to preserving your claim. If you file a construction lien in Nebraska outside of the 120-day window, your lien will be invalid. This past week, we filed a construction lien electronically in Douglas County.  This means that we submitted the lien on-line and waited for a Douglas County employee to review the lien and [...]